Answer
Apr 19, 2017 - 01:11 AM
Hi there;
Changing channel plot step can be controlled by clicking right click on your workspace, then you will see project setting option. By clicking on it, you can find the following:
1- Duration of run.
2- Solutions time step.
3- channel plot step; which is what you are looking for.
Regards
Hasan
Changing channel plot step can be controlled by clicking right click on your workspace, then you will see project setting option. By clicking on it, you can find the following:
1- Duration of run.
2- Solutions time step.
3- channel plot step; which is what you are looking for.
Regards
Hasan